List of Major Events

August 2018

The notice for prequalification of tenderers for Contract No. ED/2018/04 - Trunk Raod T2 and Infrastructure Works for Developments at the Former South Apron was gazetted on 17 August 2018.
(https://www.gld.gov.hk)

November 2015

Contract No. KL/2014/03 - Kai Tak Development - Stage 3 Infrastructure Works for Developments at the Southern Part of the Former Run Way was commenced on 23 November 2015. It is anticipated that the works will be completed by end of 2019.

December 2014

The Site Investigation Works (Stage 2) for the Project carried out under Contract No. KL/2013/02 was completed.

November 2014

Authorisation of Trunk Road T2 (7785TH) under the Roads (Works, Use and Compensation) Ordinance (Chapter 370) was gazetted on 21 November 2014.
(https://www.gld.gov.hk)

September 2013

The Director of Environmental Protection approved the Environmental Impact Assessment Report for Tunk Road T2 Project, and granted the Environmental Permit (EP-451/2013) on 19 September 2013.
(https://www.epd.gov.hk)

January 2011

The Site Investigation Works (Stage 1) for the Project carried out under Contract No. KL/2009/02 was completed.

December 2009

The investigation phase of the Project commenced.

July 2009

We appointed the Consultants - Hyder-Meinhardt-Joint Venture (HMJV) to carry out the investigation, design and construction (I, D&C) assignment for Kai Tak Development - Trunk Road T2 and Infrastructures at South Apron.

The review phase of the Project commenced.