TABLE OF CONTENTS

 

Executive Summary 1

1. INTRODUCTION Error! Bookmark not defined.

2. SUMMARY OF EM&A REQUIREMENTS AND MONITORING RESULTS Error! Bookmark not defined.

3. LANDSCAPE AND VISUAL Error! Bookmark not defined.

4. WASTE MANAGEMENT Error! Bookmark not defined.

5. SITE INSPECTION Error! Bookmark not defined.

6. ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE Error! Bookmark not defined.

7. IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES Error! Bookmark not defined.

8. Conclusions Error! Bookmark not defined.

 

 

FIGURES

 

Figure 1 Project General Layout

Figure 2 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Construction Programme

Appendix B

Project Organization Chart

Appendix C

Action and Limit Levels for Air Quality and Noise

Appendix D

Graphical Presentation of Monitoring Data

Appendix E

Waste Flow Table

Appendix F

Environmental Mitigation Implementation Schedule (EMIS)

 

 

 

 

 


Executive Summary

 

   i.   The Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

  ii.   This is the fourteenth Quarterly EM&A Report presents the environmental monitoring and audit works for the period between 1 June 2019 and 31 August 2019. As informed by the Contractor, major activities in the reporting period included:

 

June 2019

July 2019

August 2019

  Excavation and laying of drainage pipe and manhole;

  Excavation and ELS construction.

  Construction of SUS structure; and

  Construction of District Cooling System.

  Construction of Subway A.

  Construction of road base and road pavement.

 

  Excavation and laying of drainage pipe and manhole;

  Excavation and ELS construction.

  Construction of SUS structure; and

  Construction of District Cooling System.

  Construction of Subway A.

  Construction of road base and road pavement.

 

  Excavation and laying of drainage pipe and manhole;

  Excavation and ELS construction.

  Construction of SUS structure; and

  Construction of District Cooling System.

  Construction of Subway A.

  Construction of road base and road pavement.

 

 

 

Breaches of the Action and Limit Levels

 

iii.   No Action and Limit Level exceedance for 24-hr TSP and noise was recorded in the reporting period at all monitoring stations.

 

 

Complaint, Notification of Summons and Successful Prosecution

 

iv.   No environmental complaint and no notification of summons and successful prosecution were received in the reporting period.